The targets and achievement in the year 1998-99 are shown below

Sl. No. Name of the District Name of the Scheme and  Item of work Funds alloted including spillover during 98-99

Cumulative achievement for the year 1998-99

Phy. (Ha) Fin. (in Rs.) Phy. ( Ha.) Fin. (in Rs.) Mandays.
I.A

STATE PLAN

1 Kandhamal Sisal (TASP) extraction of Sisal 25 21250/- 25 21250/- 600
B.

S.C.D.C (TASP)

1 Kandhamal Main. of Pepper 1.6 1280/- 1.6 1280/- 38
2 Conservation cropping 7 9400 7 9400 219
3 Pepper nursery 1.25 1000/- 1.25 1000/- 20
4 Improvement of SCDC 1 3000/- 1 3000/- 70
  TOTAL     14680/- - 14680/- 347
C. WATER SHED DEVELOPMENT PROGRAMME (TASP)
1 Kandhamal Maint. of Coffee (Non-bearing) 48 95240/- 48 95240/- 1030
 

GRAND TOTAL OF STATE PLAN

48 131170 48 131170 1977
II STATE NON-PLAN (Water shed management unit (Non-Plan)
1 Kandhamal Maint. of W.H.S. 195 nos. 390000/- 185 370000/- 9305
2 Maint. of Gully control 10 Nos. 2000/- 10 2000/- 63
3 Maint. of Pineapple , 4 14800/- 4 14800/- 906
  Maint. of bearing coffee 14 62000/- 14 59618/-
  Non-Bearing 18 18
4 Purchase of Ag. implement - 18000/- - 18000/- -
  Sisal Plan (Nil. & Bel.)
5 Kandhamal Extraction of Sisal 67 43500/- 67 33000/- 660
  Maint. of Sisal 67 27000/- 67 27000/- 900
  Maint. of Ddecarticator 1 No. 2500/- 1 No. 2500/- -
  TOTAL - 73000/- - 62500/- 1560
  SCDC (Non-Plan)
6 Kandhamal Maint. of orchard 14 2100/- 14 2100/- 67
  Maint. of nursery 0.8 3900/- 0.8 3900/- 74
  Maint. of Farm 1 2000/- 1 2000/- 62
  Maint. of pond 1 1500/- 1 1500/- 6
  Gree fencing with sisal - 2000/- - 2000/- 66
  Cultivation of crops 4.80 24000/- 4.8 2400/- 797
  TOTAL - 35500/- - 35500/- 1070
  C.B.Land (Non-Plan) 
7 Kandhamal Layout of demonstration plot in C.B.Land 21 4000/- 10 4000/- 35
    TOTAL(1 to 7) - 599300/- - 566418/- 12939
III. D.P.A.P.            
1 Kandhamal Extension of Canal 5 Nos. 134150/- 5 134150/- 2587
IV O.S.F.D.C Ltd.
1. Kandhamal Construction of W.H.S/D.W 7 Nos 1255000/- 7 Nos 1265000/- 23502
V DROUGHT
1 Kandhamal Cross Bund 1 No 60000/- 1No 60000/- 1820
  IRRIGATION SECTOR
1 Kandhamal Diversion Weir 49 4867321/- 36 4648153/- 85437
  SOIL CONSERVATION SECTOR
1 Kandhamal Watershed Dev. guide 3417.35 55820/- 1314 Rmt 55820 1500
2   Loose boulder check dam 28 11488/- 24 52488/- 1069
3   Eathern Run off management structure 12 Nos 124462/- 3 76462/- 1667
4   Earthen check dam 8 3527/- 5 35527/- 915
5.   Shunken ponds 10 2990/- 10 2990/- 60
6   Drop spillway 1 25000/- 1 25000/- 500
7   J.L.P. 4 35000/- 1 20000/- 660
8   Bank stabilisation 7 (-) 33000/- - - -
9   Strem bank structure - - - - -
  TOTAL - - 225287/- - 265287/- 6361
  G.Total (EAS) - - 5092608 - 4913440 91798

Although much work has been done by the departments so far, it only touched the fringe of the problem. Kandhamal dist. with its unique topographical features of hills and forest, criss-crossing nallas and rivullets and unpoverished uplands, gullies and ravines offer ample scope for soil conservation measures.

MONTHLY PROGRESS REPORT ON N.W.D.P..R.A SCHEME OF 9TH PLAN PERIOD RELATING TO THE FUNDS ALLOTED DURING THE YEAR 1998-99 OF S.C. DIVISION : PHULBANI FOR MARCH-1999.

Sl. No. Name of the district. Name of the activity/ item of work with unit cost Unit Allotment 98-99 Cumulative acievement till-to-date Remarks
        Phy. Fin. Phy. Fin.  
BASIC ACTIVITIES
1 Phulbani Esst. & managemet cost. Rs. - 221000/- - 2311405/-  
2 Survey & projectisation Rs. 12 175000/- 5 121921/-  
3 Training Rs. 5 205000/- 5 173500/-  
4 Estt. of composite nursery. No. 8 85000/- 8 87000/-  
  Total - - 686000/- - 2693826/-  
ARABLE LAND : CONSERVATION MEASURES.  
1 Phulbani Contour veg. hedges 0 to 4% slope Ha. 60 11000/- 40 9000/-  
2 Repair of old S.C. works No. 858.30 25800/- 858.30 25800/-  
3 Gully control measures No. 130 130000/- 130 130000/-  
    TOTAL   - 166800/- - 164800/-  
PRODUCTION SYSTEM.
1 Phulbani Agro forestry No. 4400 12600/- 2200 9300/-  
2 Organic farming system No. 136 13600/- 131 13600/-  
3 Homestead garden No. 120 12000/- 100 10000/-  
4 Household production system No. 52 52000/- 47 47000/-  
  TOTAL   - 90200/- - 79900/-  
    TOTAL ARABLE LAND   - 257000/- - 244700/-  
NON-ARABLE LAND ( CONSERVATION MEASURES)
1 Phulbani Live fencing Rmt. 1000 10000/- 1000 10000/-  
2   Vegetative filter strips Rmt.   14000/- - 14000/-  
3   Vegetative contour hedges Ha. - 4000/- - 4000/-  
4   Gully control measures No. 207 207000/- 207 207000/-  
  Total       235000/- - 235000/-  
PRODUCTION SYSTEM
1 Phulbani Planting of tree No. - 140000/- - 72500/-  
DRAINAGE LINE TREATEMENT ( UPPER REACHES)
1 Phulbani Loose boulder check dam No. 189 94500/- 174 87000/-  
2   Small dug-out shunken pond No. 84 126000/- 79 119000/-  
    TOTAL - - 220500/- - 206000/-  
MIDDLE REACHES.
1 Phulbani Loose boulder structure No. 107 214000/- 99 198000/-  
2   Earthern structure No. 63 63000/- 63 63000/-  
3   Run-off management dugout ponds No. 55 137500/- 55 137500/-  
    TOTAL - - 414500/- - 398500/-  
LOWER REACHES
1 Phulbani Limited no. of W.H.T. No. 13 325000/- 12 300000/-  
    TOTAL - 13 325000/- 12 300000/-  
TOTAL DRAINAGE LINE TREATMENT - - 960000/- - 904500/-  
G.TOTAL OF NON-ARABLE LAND. - 1335000/- - 1212000/-  
LIVE STOCK MANAGEMENT
1 Phulbani Cultivated fooder production No. 27 17000/- 15 11000/-  
    GRAND TOTAL - - 2295000/- - 4161526/-  