| Sl. No. | Demand no/name of the road/length of the road/category | Original A/A position | year wise allotment in lakhs. | Uptodate Expend. |
Physical progress. | |||
| Metalling in Kms. | BT in Kms. | CD/Retaining wall in Mtr. | ||||||
| (A) D.No.7-5054SP | ||||||||
| i | Berhampur-Phulbani road (SH.7)112/0 to 161/88 Km. | 95-96=10.00 | 10.00 | 8.14 | 1.28 | 3.88 | - | |
| 96-97=3.00 | 3.00 | 3.00 | 1.65 | - | ||||
| 97-98= | - | - | - | - | - | |||
| 99-2000= - | - | - | - | - | - | |||
| ii | Phulbani-Tikarpada road (SH.23) from 0/0 to 30/0 Km. | 95-96=2.21 | 2.21 | 2.21 | 0.52 | 0.52 | - | |
| 96-97=1.00 | 1.00 | 1.00 | 1.00 | 0.25 | 0.25 | |||
| 97-98= - | - | - | - | - | - | |||
| 98-99= - | - | - | - | - | - | |||
| 99-2000= - | - | - | - | - | - | |||
| iii. | Banigochha-Madhapur-Khajuripada- Phulbani -Sarangada road (SH.1) 149 to 219 + 3km. Plb town road | 95-96=2.83 | 2.83 | 2.83 | 0.25 | 1.25 | - | |
| 96-97=2.00 | 2.00 | 2.00 | 0.679 | 0.20 | - | |||
| 97-98= - | - | - | - | - | - | |||
| 98-99= 5.00 | 5.00 | - | - | - | ||||
| 99-2000=- | - | - | - | - | - | |||
| iv | Kalinga-G.Udayagiri road (SH.7A) from 0/0 to 6/0 Km. | 95-96=0.50 | 0.50 | 0.50 | 0.20 | 0.20 | - | |
| 96-97= - | - | - | - | - | - | |||
| 97-98= - | - | - | - | - | - | |||
| 98-99= - | - | - | - | - | ||||
| 99-2000= - | - | - | - | - | - | |||
| v | Sankarakhole-Khajuripada road (ODR) from 0/0 to 21/32 Km. | 95-96=3.00 | 3.00 | 1.22 | 0.10 | 0.60 | ||
| 96-97=1.00 | 1.00 | - | - | - | - | |||
| 97-98= - | - | - | - | - | - | |||
| 98-99= - | - | - | - | - | - | |||
| 99-200= - | - | - | - | - | - | |||
| vi | Phulbani town circular road (ODR) 0/0 to 9/25 | 95-96=1.00 | 1.00 | 1.00 | 0.26 | 0.26 | 6.00 | |
| 96-97=1.00 | 1.00 | 1.00 | 0.45 | 0.25 | - | |||
| 97-98= - | - | - | - | - | - | |||
| 98-99= - | - | - | - | - | - | |||
| 99-2000= - | - | - | - | - | - | |||
| vii | Const. of Dev. of Gudari airstrip at Phulbani | 4.17 | - | - | - | - | ||
| BRIDGE WORKS (D.NO.7-5054 SP) Progress rpt. | ||||||||
| i. | Const. of HL Bridge over Penjisahi Nalha at 2/5-7 km. of Phulbani-Tikarpada road SH.23 | 37.27 (RAA) | 22.10 | 22.50 | Work under progress. | |||
| ii. | Const. of Summersible bridge over Nuagam Nalha at 15/0-2 Km. of Sankarakhole- Khajuripada road(ODR) | 26.964 | 13.10 | 5.50 | Work in progress | |||
| iii. | Const. of HL bridge over Baunsuni Nallah 17/4-6 Km. of Sankarakhole-Khajuripada road (ODR) | 13.965 | 29.00 | 6.10 | Work in progress. | |||
| iv. | deposit works | |||||||
| Const. of road from Jargipada to Phiringia under MPLAD scheme | 3.00 | 3.00 | - | Work to be taken up shortly. | ||||
| BUILDING WORKS | ||||||||
| Tourism deptt.(D.no.4059 & State- 7.5452 SP. | ||||||||
| i. | Const. of Dist. tourism centre at Plb. | 37.094 | 27.20 | 24.96 | Under progress. | |||
| ii | D.No.7-4216 Housing SP | |||||||
| Const. of staff qrs. for dist. tourism centre at Phulbani (1 no. E type & 1 no. F type Qr.) | 4.095 | 3.04 | 0.88 | Work under progress. | ||||
| Culture Department (D.No.7-4202 SP) | ||||||||
| Const. of Dist. Culture Centre at Phulbani | 68.24 | 26.40 | 26.40 | on Progress | ||||
| Home Deptt. (Jail) (D.no.7-4059 SP) | ||||||||
| i. | Const. of Indoor Hospital ward in Plb. jail to the medical care for prisoners. | 5.70 | 4.48 | 1.22 | On progress | |||
| ii. | Const. of workshed with storage facilities for estt. of moulded Khallileaf unit in Dist. Jail,Phulbani | 1.80 | 1.66 | 0.55 | Under Progress. | |||
| iii | Impvt. of reno. of kitchen block of Phulbani dist. jail | 1.72 | 1.72 | 0.40 | Under Progress. | |||
| iv | Constn. of 10 capacity female ward with separte enclosure at Plb. dist. jail | 4.45 | 3.42 | - | To taken up shortly. | |||
| Home (JUDICIAL) Deptt. (D.No.7-4059 | SP) | |||||||
| i | Constn. of D type Qrs. for JMFC,Plb. | 7.61 | 5.98 | 3.51 | Work under Progress. | |||
| ii | Const. of 1 no. of C type Qr. for Registrar at Phulbani. | Estimate Rs. 10 Lakhs | Submitted | for A/A & | Palcement | of funds. | ||
| iii | Constn. of 1 No. of D type qr. for SDJM at Phulbani. | -do- | ||||||
| iv | Constn. of C type Qr. for CJM,Phulbani | Tender accepted | & due to non-avialability | of site & want of | this work can't be | takneup. | ||
| v. | Const. of B type Qr. for DJ at Phulbani | 2.23 | 1.87 | 1.87 | On progress. | |||
| vi. | Constn. of Dist. Judge Court Bldgs. at Phulbani (First floor) | 109.92 | 81.85 | 81.85 | Completed | |||
| SPORTS & YOUTH SERVICE DEPTT. 7-4202 SP | ||||||||
| Constn. of SPDA at Plb. (including 14 nos. of sub-works) 1. Gymanasium hall, 2. Stadium centre trac, 3. Galarry , 4. Volly Ball Court, 5. basket Ball Court, 6. Kabadi Ground, 7. Swimming poll, 8. Sports Hostel, 9. Staff Qr.,10 booking counter, 11. Vehicle Parking, 12. Approach road to Hostel & staff Qrs. swimming pool, 13. balcony & step for VIP ,14. Approach road for VIP players. | 14.62 134.248(RE) | 37.5675 | 31.85 | Work in progress. | ||||
| Const. of Summersible bridge over Nuagam Nalha at 15/0-2 Km. of Sankarakhole- Khajuripada road(ODR) | 26.964 | 13.10 | 5.50 | Work in progress | |||
| Const. of HL bridge over Baunsuni Nallah 17/4-6 Km. of Sankarakhole-Khajuripada road (ODR) | 13.965 | 29.00 | 6.10 | Work in progress. | |||
| deposit works | |||||||
| Const. of road from Jargipada to Phiringia under MPLAD scheme | 3.00 | 3.00 | - | Work to be taken up shortly. | |||
| BUILDING WORKS | |||||||
| Tourism deptt.(D.no.4059 & State- 7.5452 SP. | |||||||
| Const. of Dist. tourism centre at Plb. | 37.094 | 27.20 | 24.96 | Under progress. | |||
| D.No.7-4216 Housing SP | |||||||
| Const. of staff qrs. for dist. tourism centre at Phulbani (1 no. E type & 1 no. F type Qr.) | 4.095 | 3.04 | 0.88 | Work under progress. | |||
| Culture Department (D.No.7-4202 SP) | |||||||
| Const. of Dist. Culture Centre at Phulbani | 68.24 | 26.40 | 26.40 | on Progress | |||
| Home Deptt. (Jail) (D.no.7-4059 SP) | |||||||
| Const. of Indoor Hospital ward in Plb. jail to the medical care for prisoners. | 5.70 | 4.48 | 1.22 | On progress | |||
| Const. of workshed with storage facilities for estt. of moulded Khallileaf unit in Dist. Jail,Phulbani | 1.80 | 1.66 | 0.55 | Under Progress. | |||
| Impvt. of reno. of kitchen block of Phulbani dist. jail | 1.72 | 1.72 | 0.40 | Under Progress. | |||
| Constn. of 10 capacity female ward with separte enclosure at Plb. dist. jail | 4.45 | 3.42 | - | To taken up shortly. | |||
| Home (JUDICIAL) Deptt. (D.No.7-4059 | SP) | ||||||
| Constn. of D type Qrs. for JMFC,Plb. | 7.61 | 5.98 | 3.51 | Work under Progress. | |||
| Const. of 1 no. of C type Qr. for Registrar at Phulbani. | Estimate Rs. 10 Lakhs | Submitted | for A/A & | Palcement | of funds. | ||
| Constn. of 1 No. of D type qr. for SDJM at Phulbani. | -do- | ||||||
| Constn. of C type Qr. for CJM,Phulbani | Tender accepted | & due to non-avialability | of site & want of | this work can't be | takneup. | ||
| Const. of B type Qr. for DJ at Phulbani | 2.23 | 1.87 | 1.87 | On progress. | |||
| Constn. of Dist. Judge Court Bldgs. at Phulbani (First floor) | 109.92 | 81.85 | 81.85 | Completed | |||
| SPORTS & YOUTH SERVICE DEPTT. 7-4202 SP | |||||||
| Constn. of SPDA at Plb. (including 14 nos. of sub-works) 1. Gymanasium hall, 2. Stadium centre trac, 3. Galarry , 4. Volly Ball Court, 5. basket Ball Court, 6. Kabadi Ground, 7. Swimming poll, 8. Sports Hostel, 9. Staff Qr.,10 booking counter, 11. Vehicle Parking, 12. Approach road to Hostel & staff Qrs. swimming pool, 13. balcony & step for VIP ,14. Approach road for VIP players. | 14.62 134.248(RE) | 37.5675 | 31.85 | Work in progress. | |||
| FINANCE DEPTT. 7-4059(SP) | |||||||
| Constn. of computerisation of Dist. Treasury at Plb. | 5.9 | 2.03 | 2.03 | Work completed except of AC machine | |||
| REVENUE & EXCISE DEPTT. | |||||||
| Const. of record room for Tahasil office, kandhamal at Phulbani | 4.00 | 3.86 | 1.05 | Work in progress | |||
| D.no.7-4216 SP | |||||||
| S/R to revenue Qrs. at Phulbani located at Treasury Road,Nadikhandi sahi | 2.75 | Work will be taken up after receipt of the funds. | |||||
| D.No.7-4059 SP | |||||||
| S/R to Tahasil office bldg. at Kandhamal | 1.327 | do/- | |||||
| S/R such as providing grading plaster and tartelting to Collectorate building,Plb. | 2.75 | Work completed partly , balance work will be taken up after receipt of funds. | |||||
| Health Deptt. (7-2216 SP) | |||||||
| Constn. of post mortum centre at Plb. | 3.33 | 3.33 | 0.55 | Work in progress | |||
| S/R to DHH such as constn. of OT corridor. | 1.5 | 1.5 | 1.0 | Work in progress. | |||
| Education Deptt. (7-4202 SP) | |||||||
| S/R to Govt. College at Plb. providing MS grill gate & cow catcher | 2.5 | 2.5 | 0.5 | Work in progress | |||
| Constn. of compound wall for SM Womens' College,Phulbani | 4.05 | 4.05 | 2.41 | Work on progress | |||
| S/R to Govt. College Bldgs. at Plb. (Compound Wall) | 0.50 | 0.50 | 0.25 | -do- | |||
| Const. of Institution bldgs. for DIET at Tikabali | 8.74 | 7.57 | 7.57 | completed | |||
| Constn. of staff qrs. for DIET at Tikabali | 7.68 | 9.74 | 8.393 | do | |||
| Constn. of DIET hostel bldgs. at Tikabali | 23.46 | 17.99 | 17.99 | do | |||
| Panchayat raj Deptt. | |||||||
| Constn. of E type Qr. for DPO,Plb. | 1.96 | 1.4 | 1.4 | completed except door,window shutter & grill. | |||
| Labour & Employment Deptt. | |||||||
| Constn. of approach road for DEO,Plb. | 1.405 | 0.50 | 0.1 | work in progress. | |||
| Deposit Works. | |||||||
| Constn. of compound wall of Mini stadium at Tikabali under MPLAD(96-97) | 2.5 | 1.75 | 0.75 | Work in progress | |||
| Constn. of study room for Life Sc. in Govt. College,Plb. under MPLAD(96-97) | 1.00 | 0.5 | 0.5 | Work in progress. | |||
| S/R to Panchayat Bhawan at Plb. such as providing GYPSUM board ceilling with Al. frame to the existing conference hall. | 2.50 | 2.50 | 2.50 | Completed. | |||
| Black topping of approach to DHH & attendants, REst shed at TB word at Plb. (MPLAD) | 2.00 | 2.00 | - | Work to be taken up after receipt of A/A for the work. | |||